Total Pageviews

Sunday, October 18, 2015

SERVICE TO THE FLEET Turns 70 Years Old Today


Blog #62.  October 18, 2015 by Marcus W. Robbins

Full content of this blog is now shown on my main Norfolk Navy Yard website:
 
http://www.usgwarchives.net/va/portsmouth/shipyard/nnyblogindex.html

SERVICE TO THE FLEET mastheads are kindly provided courtesy of Portsmouth Naval Shipyard Museum library.
 

Sunday, October 4, 2015

The United States Navy’s 240th Birthday

Blog #61.  October 4, 2015 by Marcus W. Robbins

Full content of this blog is now shown on my main Norfolk Navy Yard website:
 
http://www.usgwarchives.net/va/portsmouth/shipyard/nnyblogindex.html

Image Courtesy of the Naval History & Heritage Command

Sunday, September 6, 2015

History and Facts About the 350 Ton Hammerhead Crane

Blog #60.  September 6, 2015 by Marcus W. Robbins

Full content of this blog is now shown on my main Norfolk Navy Yard website:
 
http://www.usgwarchives.net/va/portsmouth/shipyard/nnyblogindex.html


Hammerhead Crane, publicly released, signed and dated 12/9/1940
(Original Photo Courtesy of Marcus W. Robbins collection)

Wednesday, August 26, 2015

Receiving Ship USS Franklin at Saint Helena

Blog #58.  July 12, 2015 by Marcus W. Robbins

Full content of this blog is now shown on my main Norfolk Navy Yard website:
 
USS Franklin & USS Richmond at Saint Helena
Norfolk Navy Yard (circa 1908)
(Courtesy of Marcus W. Robbins collection)

 

350 Ton Hammerhead Crane, Alternatives and Public Information Meeting

Blog #59. August 23, 2015 by Marcus W. Robbins

Full content of this blog is now shown on my main Norfolk Navy Yard website:
 
http://www.usgwarchives.net/va/portsmouth/shipyard/nnyblogindex.html


Public Information Meeting August 18, 2015 ~ Tri-fold (front cover and rear text)                                   


Saturday, June 20, 2015

182 Years Ago ~ Docking of the USS Delaware at Gosport

Blog #57.  June 20, 2015 by Marcus W. Robbins

The USS Delaware rated at 74 guns was both born and then later died at the Gosport Navy Yard yet still it lives on today. 

With a history like no other American ship, subjected to some classic moments it is a proud journey, most noted for becoming the first ship in the Western Hemisphere to be dry docked on June 17, 1833 at the Gosport Navy Yard, Portsmouth Virginia.

But every good story must have a beginning and so in August of 1817 the keel of a line-of-battle ship was laid.  The timber for this ship had been in store for years, having been collected under the provisions of the Act of Congress of February 25, 1799 and subsequent amendments.  The name after ward chosen by lottery for this ship was "Delaware."

USS Delaware was built on the same site of construction of the USS Chesapeake in the extreme north end of the present shipyard.  This would be very close to today’s Building 74 footprint across from Trophy Park.  As when I used to conduct walking history tours at NNSY it was amazing to stand in this area and point and say – “this ship was built here, this structure burned there, this ship sank here” as so much of America’s notable early naval history is concentrated in just a few acres of river front.

Ship building at the time was a much different than today, slower and with much manual labor and while no photographs were in existence to capture the moment the below painting by Joshua Shaw in 1820 does give us a glimpse of USS Delaware construction at early Gosport.
 
 
Norfolk; From Gosport, Virginia
(Courtesy of The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library Digital Collections)
(Accessed on June 20, 2015 by MWR)
The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064
The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-
 
On October 21, 1820, the USS Delaware was launched and housed over, not being required for service immediately.  The ship stays in ordinary and is housed over (a sort of mothballing) till March 27, 1827 as to finally receive orders to be put to sea.

Sailing on February 10, 1828 to the Mediterranean the USS Delaware makes a successful journey back to Gosport on January 2, 1830 and again is layed up in ordinary to await further orders.  In 1833 those order arrive to prepare to sail again.

Yet things were changing at Gosport, the new nation was about to have its first dry dock.  The prior method of a ship being careened to its side for the purpose of undergoing repairs to its hull beneath the waterline as about to end.  Think of the physical strain to the ship by tugging and pulling it out its element like a stranded beached whale.  Yet it is a necessary evil to tend to the unseen conditions.  The hull of a ship can be attacked by all sorts of marine growth and once you have a problem, well it can accelerate quickly if not attended to.  As a means to prolong a ship’s lifespan it was customary to sheath the hull fully with thick copper sheets fastened by copper nails yet this could only prolong the onset of maintenance and repair.

As I discussed in “History Matters” Blog #36 Gosport would soon benefit from legislation entitled “An Act for the Gradual Improvement of the Navy of the United States” passed on March 3, 1827.  The shipyard would grow both to the West and more importantly to the South as additional land was purchased in order to create a place to construct the dock.

Our Dry Dock 1 can be attributed to the one of the young country’s finest civil engineers at the time, Colonel Loammi Baldwin Jr. Baldwin in his personal profession had made two different trips to Europe studying and examining public works, the last being in 1824.  This coincided with a report of the Secretary of the Navy urging the building of two dry-docks in America that was presented on May 25, 1825 thus the die was cast leading to his acceptance of an appointment to oversee the construction of the new dry-docks at the Charlestown Navy Yard in Boston, Massachusetts and the Gosport Navy Yard in Portsmouth, Virginia between the years of 1827 & 1834.

Colonel Baldwin was one of a family of engineers, all more or less distinguished in their profession. He had visited many of the dry docks of Europe, and was particularly qualified for the work which he afterward preformed of building the docks at Gosport and Charlestown (Lull 1874).

On the 17th of June, 1833, the anniversary of the battle of Bunker Hill, the dock was opened for the reception of the line-of-battle ship "Delaware," the first liner built at Gosport, and the first national ship ever docked in a dry dock belonging to the United States.

First Dry Docking in the Western Hemisphere
Gosport Navy Yard, June 17, 1833
(Courtesy of The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99Marcus W. Robbins collection)
 
Large numbers of ladies and gentlemen were present to witness the opening ceremonies, which were made as imposing as possibly, the occasion being one of great rejoicing as well to the citizens of Norfolk and Portsmouth as to the whole navy.

The ship sails a few more times till fate finds it along the shore at Gosport on April 21, 1861.  This is the fact where I refer to this becomes USS Delaware’s place of death.  The Union burn and scuttling of 11 ships renders the end to the once proud ship as it lies in ruins both burned and sunk south of the stone dock.  By the description of the below northern issued weekly periodical it incorrectly places the initial destruction on the Confederates (May 10th of 1862).
The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99
 
Remains of the Frigates Delaware and Columbus
(Courtesy of The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99The New York Public Library. "Norfolk, from Gosport, Virginia." New York Public Library Digital Collections. Accessed June 20, 2015. http://digitalcollections.nypl.org/items/510d47db-9e8d-a3d9-e040-e00a18064a99Marcus W. Robbins collection)

Yet today the spirit of the USS Delaware lives on.  You can see a remarkable scale model of at the Portsmouth Naval Shipyard Museum, constructed by the craftsmen at the old Norfolk Navy Yard.  There is a small tag from when it graced the Building 33 museum years ago that reads:

NORFOLK NAVY YARD 1925
BUILT BY BOAT SHOP
RIGGED BY RIGGERS SHOP
PORTSMOUTH, VA
 

Full Rigged Model of USS Delaware, 74 gun ship-of-the-line
(Courtesy of Portsmouth Naval Shipyard Museum)
Photo by Curator of History ~ Diane L. Cripps on June 19, 2015
 
USS Delaware began its life here in 1817, then made history with the first dry docking in the Western hemisphere 182 years ago in 1833 and ultimately met its death in 1861.  The vessel is forever tied to our shipyard here on the Southern Branch of the Elizabeth River because - “history matters”.

Sunday, June 14, 2015

Construction Details of the Stone Dock at Gosport

Blog #56.  June 14, 2015 by Marcus W. Robbins
 
The USS Delaware was the first ship in the Western Hemisphere to be dry docked on June 17, 1833 at the Gosport Navy Yard, Portsmouth Virginia.  The dock was not yet quite finished when this occurs 182 years ago this week.  The dock takes almost six years and 4 months to construct.
 

USS Delaware Entering the Stone Dock ~ June 17, 1833
(Courtesy of United States Navy)

Today represents my third installment retracing the entire history of Dry Dock #1 with my "History Matters" writings.  Previously, Blog #36 of August 16, 2014 - The Earliest History of Dry Dock 1 defined the need & Blog #52 of May 15, 2015 - 188 Years Ago ~ Commencement of Dry Dock 1 at Gosport reviewed the funding and chose the site.  This current blog shall detail the actual construction of the Stone Dock. 

If you wish to read my two prior referenced Blog #’s 36 & 52 they may be found here:

Today I shall provide you with text written by the Navy in 1874 as it contains some of the most comprehensive and accurate details concerning the actual construction of the Stone Dock.

From survey and turning the first spade of earth in November of 1827 to placement of the final granite stone blocks and thus being called completed on 15 March 1834 the old Stone Dock at the Gosport Navy Yard ultimately supports one of the most significant historic events of naval history for the then young United States, the first dry docking in the Western Hemisphere.

We hold June 17, 1833 in very high regard with the docking of USS Delaware as we beat the Boston Navy Yard by an entire week with their docking of the USS Constitution in their Stone Dock.  Another of a long line of our “first” accomplishments for the Navy here at Norfolk.

The following construction text is extracted and transcribed here exactly as written in 1874.  It is as close to a first generation primary source that we have today that documents the early history of the Gosport Navy Yard and the construction of the Stone Dock.
 

History of the United States Navy-Yard at Gosport, Virginia,
(Near Norfolk)

By Edward P. Lull, A. M.,
Commander, United States Navy
For the Bureau of Yards and Docks, Navy Department

Rear-Admiral C. R. P. Rodgers, U. S. N., Chief of Bureau

Washington: Government Printing Office,
1874.

Full text of this entire publication may also be found at the below link: http://www.usgwarchives.net/va/portsmouth/shipyard/nnybooks1.html


History of the United States Navy-Yard At Gosport, Virginia
(Courtesy of Marcus W. Robbins Collection)


CONSTRUCTION OF THE DRY-DOCK.

The work upon the dry-dock was commenced in November, 1827. Colonel Baldwin was appointed engineer in charge of the construction of this as well as of that authorized at Boston; and Capt. W. P. S. Sanger was appointed resident engineer at Gosport. Captain Sanger continued the immediate charge of the work under Colonel Baldwin until its completion, and to him the writer is indebted for the most of the following information on the subject, a part of which, derived from the same source, was published some years since by Mr. Charles B. Stuart.

The northernmost of the three sites selected for docks in the plan was chosen for the one about to be built. As will be seen by reference to the plan, the site as laid down projected about 130 feet outside of the shore-line or into about 10 feet of water. The average surface of the ground inside the shore-line was 6 feet above high-water mark.

COFFER-DAM.

A strong water-tight coffer-dam was built as a preliminary step to beginning the excavation; this consisted of two rows of piles 12.5 feet apart, directly in front of the dock, and 8 feet apart at the sides. Each row consisted first of ribbon-piles 14 inches square and 45 feet long, driven 8 feet apart, to which were bolted ribbons of 12 by 14 inch yellow-pine timber, one at the. head of the piles, one 6-1/2 feet, and one 10-1/2 feet lower; inside of the ribbons, i. e., toward the interior of the dam, were driven sheet-piles 13 inches square, and tongued and grooved. The rows were then secured to each other by tie-beams laid across and secured to the heads of the ribbon-piles; and by 2-inch iron bolts through the lower ribbons, one between each two of the ribbon-piles. The intervening space between the rows was then filled with clay from the excavation. The dam was found to be perfectly tight and secure, and never gave any trouble while in use.

COB-WHARF.

Joining on to the coffer-dam, on either side, was constructed a cob-wharf; that to the southward extended only some 40 yards when it turned in to the shore; but that to the northward extending along the proposed line of the quay-wall to the entrance of the proposed timber-dock, where it joined a crib-work built along the line designated for the south wall of the latter.

SOIL AND EXCAVATION.

The excavation for the dock was now pushed steadily forward, and the earth removed was used to fill in from the shore-line to the cob-wharf above mentioned, and to level other portions of the yard.  The [33] soil for a depth of from 5 to 12 feet was a yellow sand; next a stratum of fine compact blue clay, with here and there upon its upper surface irregular strata of blue sand, and of shells mixed with clay. The blue clay extended at the entrance of the dock about 30 feet below the bottom of the pit, and at the head diminished to 15 feet, where a bed of gravel was reached, so hard that an auger would not penetrate it. The pit was, when the excavation was finished, 40 feet deep, 340 feet long, and 100 feet wide at the bottom; the sides sloping so as to make it about 60 feet wider, and as much longer at the top. A chalybeate spring was met in the excavation, the flow of which was so strong as to force the water through the pores, of the piles which were driven. An auger-hole being bored in the head of a pile, the water would flow out of it freely. The summit of this spring was some six feet below the level of the low-water mark.

FOUNDATION OR BEARING PILES.

The pit having been prepared, foundation or bearing piles were driven in rows 3 feet apart from center to center, but somewhat closer along the central line of the pit. These piles were about 30 feet long at the entrance, and gradually diminished in length to 15 feet at the head, being driven down to the stratum of gravel above referred to, into which it was impossible to make them enter more than a few inches. A row of sheet-piles was next driven across the head and along either side of the pit, a row across the front entrance, one under where the grooves for the floating-gate were to be, one under the turning-posts of the gates, and one under the gallery. These rows of sheet-piles act both as stop-waters and as additional supports to the foundation.

FOUNDATION.

The heads of the bearing-piles were cut off level, and upon them were placed, transversely with the axis off the dock, yellow-pine beams 12 inches thick either way, and secured to the piles by treenails. The spaces between the beams and to the level of their upper surfaces were then filled with broken stone, after which a close floor of 4-inch yellow-pine plank was laid, and upon this and directly over .the lower was placed a second course of timber 12 inches thick by 16, laid edgewise; the intermediate spaces between these were filled with brick laid in cement, after this another floor similar to the first was put down.

MASONRY.

All the dimension stone of this dock is of granite from different Massachusetts quarries, and nearly all of it was dressed in the quarries from the plans, and so well was this work done that it is estimated that not $100 were spent in altering stone. The rubble-backing to the side-walls was obtained principally from the quarries at Port Deposit, Md. A small portion, however, came from the Falls of the James River, near Richmond.

[34] The chamber of the dock, or the portion ordinarily used for docking ships, is 253 feet long and 85-1/2 feet wide at the coping. The extreme length of the dock, which can be made available by placing the floating-gate outside the entrance and not using the turning-gates, is 320 feet. The United States ship Severn, measuring 324 feet over all, was recently docked by blocking up to raise her above the miter-sills. The floor of the chamber is 227 feet long and 30 feet wide. The increase in the width of the chamber from the floor to the coping is produced by offsets in the side-walls forming the altars. The side-walls are 35 feet thick at the bottom and but 7 at the coping. The floor is laid in two courses of cut granite in the form of an inverted arch, to resist the upward pressure of the water; the lower course is tapering in form, 1 foot thick at the entrance of the chamber and 2 feet 3 inches at the head, thus giving a rise of 1 foot 3 inches; the second course is of uniform thickness, i. e., 3 feet.

The lowest two altars have a rise of 15 inches each, the floor rising to the level of the lowest altar at the head of the chamber; the next three have a rise of 1 foot each. These five altars are laid so as to form a continuation of the inverted arch; the next three rise 3 feet each; the next three, 4 feet 4-1/2 inches each; when a further rise of 4 feet 4-1/2 inches brings us to the coping. The width of the altars from the lowest up are as follows: The first, 3 feet; the next three, 2 feet each; the next, 4 feet; the next two, 2-1/2 feet each; the next, 4 feet; and the upper three, 2 feet each. The head of the chamber is semicircular. There are five timber-slips in the head of the dock, with landings upon the broad altars. There are six flights of stone stairs in the chamber for the use of workmen, three on each side, viz, one at the head; one at the center; and one at the entrance. At the entrance of the chamber is the gallery, which is the lowest part of the floor, and from which the water passes through gates into the discharging-culverts. Next, outside the gallery, is the great inverted arch; the miter-sills against which the turning-gates rest when closed, abut against this arch. Vertical recesses in the side-walls receive the turning-gates when open. Outside of these recesses, at the entrance of the dock, is another inverted arch, a groove in which, and continued up the side-walls, receives the floating-gate. The floating-gate may, however, as has been mentioned above, be placed against shoulders in the face of the entrance, thus increasing the capacity of the dock.

CULVERTS.

On either side of the dock a culvert 4 feet high and 2-1/2 feet wide in the opening, and provided with a bronze gate, leads from the gallery to the reservoir across the head of the dock; the culverts are built of hard brick laid in cement, with straight side-walls and semicircular tops and bottoms; the thickness of the walls is 14 inches.

The reservoir is 12 feet high and 7 feet wide, built with straight side- [35] walls of cut granite, a semicircular top of brick 14 inches thick, and a brick inverted arch at the bottom of the same thickness.

From the south end of the reservoir, (where a well is situated, reaching to the surface,) a tunnel, with cross-section elliptical in form, 4 feet high and 2 feet 9 inches wide in the opening and about 190 feet long, leads to the pump-well. From the pump-well a discharge-culvert about 150 feet long leads into the creek at the southwest corner of the yard; it is about 4 feet square at the mouth, and supplied with a composition gate.

Water is admitted to the dock through filling-culverts, one on either side, 14 feet 9 inches below the coping, and leading inside of the turning-gates; these culverts also are supplied with bronze gates.

PUMP-WELLS AND ENGINE-HOUSE.

There are two pump-wells 15 feet 9 inches in diameter each, and connected together; they are built of brick; the bottoms are inverted arches, 2 feet thick; the side-walls are 2-1/2 feet thick, with four projecting courses of cut stone at proper intervals to support the pump-frames. On the tops of the walls are stone copings 1 foot deep and 18 inches wide.

There are four lift-pumps in each well, each 30 inches in diameter and of 3 feet stroke, made of cast iron, lined with composition staves and supplied with composition boxes and valves. The pumps are driven by pinion-wheels fitted on either end of the engine-shaft, working in cog wheels on the shafts of the pumps.

The engine-house was a two-story brick building, 200 feet long by 50 feet wide; but 50 feet of the lower story was used for the lifting-engines; the rest of the building was at first occupied as a saw-mill and as a machine-shop. The whole is now used as a machine-shop.

GATES.

The turning-gates are constructed of timber and composition, and covered with copper. Each gate is 36 feet wide and 30 feet 8 inches in height. The turn-posts are fitted with composition saucers in the lower ends, which rest upon composition pintles fixed in the masonry; the tops of the posts are secured in place by straps keyed to anchors laid in the coping. Each gate is supplied with two composition rollers, and cast-iron tracks are laid upon the floor for these to travel upon.

FLOATING GATE.

The floating-gate, or caisson, is built of white-oak timber and yellow pine plank, copper-fastened. It is 60 feet long, 30 feet high, and 16 feet wide amidships. The stems and keel are each 2 feet thick, and project 14 inches into the grooves in the walls and arches. There is a fore-and-aft bulk-head from stem to stern and from deck to keelson, composed [35] of solid timber, and 2 feet thick. Three courses of tie-beams from this bulk-head to the sides resist the pressure of the water Four copper ship's pumps on each side, and worked by brakes on deck, are used for pumping out the water when it is desired to lift the gate out of the grooves.

On the 17th of June, 1833, the anniversary of the battle of Bunker Hill, the dock was opened for the reception of the line-of-battle ship Delaware, the first liner built at Gosport, and the first national ship ever docked in a dry-dock belonging to the United States.

Large numbers of ladies and gentlemen were present to witness the opening ceremonies, which were made as imposing as possible, the occasion being one of great rejoicing as well to the citizens of Norfolk and Portsmouth as to the whole Navy.

The line-of-battle ship North Carolina was soon afterward admitted to the dock.

The dry-dock was turned over to the commandant of the navy-yard complete on the 15th of March, 1834. The total cost of the work was $974,356.65. The following is a tabulated statement of expenditures up to October 1, 1833, as published in the report of the Secretary of the Navy for that year.



ITEMS
AMOUNTS
Offices, shop, and stables
$22,119.75
Tools, lighters, driving-machines, &c
41,420.44
Pine-timber, plank, mails, iron, &c
17,794.34
Surveys and plans of navy-yards
*3,360.26
Coffer-dam
23,532.84
Pier wharves
10,972.50
Cob-wharves
*14,022.59
Excavation
58,572.33
Foundation
64,097.46
Drainage, (temporary)
33,803.46
Masonry of dock
450,789.62
Banking up
11,432.72
Wells and tunnel
13,762.02
Engine-house
33,901.97
Engine and pumps
27,945.22
Turning-gates
22,588.43
Floating-gate
24,121.54
Removal of coffer-dam
8,134.81
Miscellaneous
35,010.55
Superintendence
31,256.88
TOTAL
943,645.73

 




* These items not belonging properly to the dock, their cost should not be included. The engine-house was used for other purposes also, so that part only of its cost should be charged to the dock.



 
And now in closing I leave you with these last thoughts.

The monies expedited for the Stone Dock were accounted for, right down to the penny.  Ledgers were balanced and only things charged to actually support the dock were placed on the final cost, yet the above table represents cost as of 1 October 1833.  These accounting practices we could stand to practice today but looking back it is amazing to see a final cost of the Stone Dock at Gosport was declared at $974,356.65.

 

Stone Dock & Surrounds ~ Station Map of August 31, 1858
(Courtesy of Portsmouth Naval Shipyard Museum)
Photo by Curator of History ~ Diane L. Cripps on June 13, 2015


The above rare linen map shows what the Stone Dock and surrounding area really looked like as of August 31, 1858 just 25 years after the docking of the USS Delaware  and just before the Civil War.

This is a rare surviving station map that was not totally consumed by the fires of 1861 or 1862 but it has possible evidence of same, a true survivor!  It is by observing old maps such as this we can accurately document our earliest facility construction history including the old Stone Dock because - "history matters".